Festo Automation Center

Location

Festo Campus 1, 73734 Esslingen am Neckar, Germany

Principal Use

Office

Design Architect

Architekturbüro Jaschek

Anything about the engineers? Facade consultants?

Festo, the building services engineers Pfeil + Koch, the Fraunhofer Institute for Building Physics IBP, and Schindler on the execution side with a Festo-specific system application from Schüco.

Gross Floor Area

12,000 m2 Units SI IP

129,168 ft2

Reason(s) for inclusion

Building Name

Festo Automation Center

Address

Festo Campus 1, 73734 Esslingen am Neckar, Germany

Description / Additional Information

Describe the key innovation and technology aspects of the project

Project Narrative

Festo automation center is a 12000 m2 high-rise office building with a facade area of 8500m2, fully glazed with no external protection from the sun. The facade system consists of two kinds of windows: air exhaust and parallel hinged windows. An integrated building and facade concept ACT was developed based on the principle of the classic exhaust air facade, which consists of fixed glazing and internal sun protection. The intelligence lies in the control systems and extensive fine-tuning of the details to regulate the flow.

General Information

Year completed (or major renovation)

2015

Climate Zone

Temperate

External Links

Link(s) for more information

Other Design Features

Energy Performance

Construction Type

Construction Type

  • Massive Facade Construction
  • Curtain Wall

Prevalent Glazing Type

  • dynamic glass

Main Cladding Material

  • Glass
  • Aluminum

Approximate WWR (measured from the inside)

1.0%

Typical U-value Glazed Facade Elements

1 W/(m2⋅K)

0 Btu/(h·ft2⋅F)

Skin Type

Skin Type

  • Another skin

Solar Shading

Solar Shading Strategy

  • Glazing-integrated Shading

Glazing-integrated shading

  • Electrochromic Glazing

Ventilation

Is there natural ventilation through the facade?

Yes

Type of Ventilation Strategy

  • Double sided

Relationship to Mechanical Systems

  • Assisted (both can work simultaneously)

Ventilation Operation Type

  • BMS controlled with overrides

Ventilation Control Strategy

  • Based on Outdoor Air Temperature

Daylight

Is daylight simulation part of the design process?

Yes

Supporting simulation

Daylight-Simulation.jpg

Noise

Embodied Carbon

Was a carbon assesment of the facade conducted in the design phase?

No

Energy Generation

Does the facade produce energy?

No

Insulation

Active or Passive?

Monomaterial envelope?

Yes

Material

  • Other (please specify)

Description / Additional Information